HomeMy WebLinkAbout07. CIP 19-30 & 19-31 Accpt Work for Discovery & Furman Parks Improvement Projects-File NOCI Ii MI-11 04
APPROVED BY
MY MANAGER
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: OFFICE OF THE CITY MANAGER
BY: JOHN OSKOUI, ASSISTANT CITY MANAGER
1r r
SUBJECT: ACCEPTING COMPLETION OF DISCOVERY PARK AND FURMAN PARK
IMPROVEMENTS PROJECT (CIP NO. 19-30 AND CIP NO. 19-31) AS COMPLETE
AND AUTHORIZING THE ASSISTANT CITY MANAGER TO ISSUE AND FILE A
NOTICE OF C
It is recommended that that the City Council:
Accept the Discovery Park and Furman Park Improvement Project (CIP No. 19-30
and CIP No. 19-31) as complete.
2. Approve the final construction contract amount of $6,955,436.76 which includes *tt
cost of all issued contract change orders.
3. Authorize a budget adjustment for the Discovery Park Improvements (CIP No. 19-30)
from the previously approved amount of $2,600,000 to $2,639,046.
On April 9, 2019, the City Council approved the plans and specifications for the subject project
and granted authority to advertise for bids. On July 23, 2019, the City Council awarded a
construction contract to Environmental Construction, Inc. in the amount of $6,485,620.00 for
completion of work per approved plans and specifications.
x�*
Environmental Construction, Inc. started the project at Discovery Park on September 3, 2019.
Work to provide one synthetic turf soccer field (Field No. 1); one natural turf soccer field (Field
No. 2); new irrigation system; existing 20-foot high soccer ball containment netting along the
perimeter of fields, upgrade 8 metal halide light fixtures to LED fixtures at Field No. 1; new
concrete walkway along northern side of soccer fields to create connections to existing
sidewalks, two 10' x 10' storage containers; new trash enclosure; installation of site furnishing
(picnic tables, BBQs, benches, trash receptacles, and drinking fountains); and other
ACCEPTING COMPLETION OF DISCOVERY PARK AND FURMAN PARK IMPROVEMENTS PROJECT (CIP NO.
19-30 AND CIP NO. 19-31) AS COMPLETE AND AUTHORIZING THE ASSISTANT CITY MANAGER TO ISSUE
AND FILE A NOTICE OF COMPLETION
JULY 28, 2020
PAGE 2
miscellaneous related work was completed on April 2, 2019. There were seven (7) change
orders added to the scope of this project, including windscreen for the temporary fence, a
potable water connection and meter, tree trimming for ball safety netting, additional turf areas,
and added enhancements to the synthetic field and monument sign.
The total cost of construction for Discovery Park is $2,277,191.19. The project's total cost is
$2,639,045.79 (Attachment A).
Environmental Construction, Inc. started construction activities at Furman Park on September 3,
2019. Work included upgrades to Building No. 1 and Building No. 2, conversion of existing
accessible unisex restrooms, construction of one (1) new attached restroom structure;
installation of a new irrigation system; installation of new turf at softball fields; upgrade of the
primary park entrance; resurfacing of 3 tennis courts and converting one tennis court to an all -
sport court; resurfacing the existing parking lot and expanding it by adding twenty-two (22) new
stalls at southern side of the park; replacing 2 large picnic shelters with 1 new large and 3 new
medium size picnic structures; replacing the trash enclosure with new masonry enclosure to
hold 8 roll -off bins; installing site furnishings (picnic tables, BBQs, benches, trash receptacles
and drinking fountains; and other miscellaneous related work was completed on July 2, 2020.
There were ten (10) change orders added to the scope of this project, including windscreen for
temporary fence, additional turf area preparation, removal and disposal of existing beams,
additional drinking fountain and bottle filler, path and shade structure revisions, additional soils
excavation, electrical service panel upgrade, improvements to the tot lot, additional
decomposed granite on walking trail, monument sign enhancements, additional concrete
drainage structure, installation of additional filter for irrigation system, and electrical to HVAC
units.
The total cost of construction for Furman Park is $4,678,245.57. The project's total cost is
$5,391,626.12 (Attachment A).
Construction work including the original scope of work has been completed in a satisfactory
manner and in accordance with the approved plans and specifications. As such, it is
recommended that the City Council accept the Discovery Park and Furman Park Improvements
Project, CIP Nos. 19-30 and 19-31, as complete, approve the final construction cost of
$6,955,436.76, and authorize the Notice of Completion to be filed with the County of Los
Angeles Recorder's Office.
Efficiency & Adaptability
Quality of Life, Neighborhood & Infrastructure
The City's 2018-20 Capital Improvement Program includes the Discovery Park Improvements
and Furman Park Improvements Project utilizing Measure S Funds (Account Numbers 33-1-
3340-0520 and 33-1-3350-0520). The estimated budget for the subject project was
ACCEPTING COMPLETION OF DISCOVERY PARK AND FURMAN PARK IMPROVEMENTS PROJECT (CIP NO.
19-30 AND CIP NO. 19-31) AS COMPLETE AND AUTHORIZING THE ASSISTANT CITY MANAGER TO ISSUE
AND FILE ANOTICE QFCOMPLETION
JULY28.2D2D
PAGE
$8,000,000.00. The total cost for the project, including construction, design, inspection,
construction engineering and management services, material testing, abatement and contract
administration is $8,030,671.91. The required additional funding in the amount of $ 30,671.91
will be allocated from the Measure S program funds.
ATTACHMENTS
ACCEPTING COMPLETION OF DISCOVERY PARK AND FURMAN PARK IMPROVEMENTS PROJECT (CIP NO.
19-30 AND CIP NO. 19-31) AS COMPLETE AND AUTHORIZING THE ASSISTANT CITY MANAGER TO ISSUE
AND FILE A NOTICE OF COMPLETION
JULY 28, 2020
PAGE 4
Discovery Park Base Contract Amount $2,062,875.00
Change Order No. 1 (10/03/19) — Temporary fence windscreen $4,402.20
Change Order No. 2 (11/25/19) — Potable water connection $123,386.55
Change Order No. 3 (01/15/20) — Potable water meter, tree trimming $19,706.33
Change Order No. 4 (01/15/20) — Schedule extension (weather delay) $0.00
Change Order No. 5 (02/03/20) — Additional turf areas, irrigation repair $17,422.86
Change Order No. 6 (03/06/20) — Downey logo on synthetic field $45,580.25
Chance Order No. 7 (03/25120) — Monument sign veneer $3,818.00
DISCOVERY PARK TOTAL $2,277,191.19
Furman Park Base Contract Amount
Change Order No. 1 (10/03/19) — Temporary fence windscreen
Change Order No. 2 (10/09/19) — Turf preparation, beam removal
Change Order No. 3 (12/11/19) — Drinking fountain & bottle filler,
shade structure revisions
Change Order No. 4 (01/15/20) — Soils report excavation, electrical
service panel location & space
Change Order No. 5 (01/15/20) — Schedule extension (weather delay)
Change Order No. 6 (02/03/20) — Tot Lot concrete replacement, trail
enhancements, switch to hydroseed
Change Order No. 7 (03/06/20) — Schedule adjustment
Change Order No. 8 (04/24/20) — Tot Lot fence removal, drinking
fountain & bottle filter location,
monument sign veneer, concrete
drain boxes at sumps
Change Order No. 9 (05/07/20) — Trellis location & column removal,
strainer & filter for silt and particles
Change Order No. 10 (05/29/20) — Paint existing backstop, electrical
to HVAC units $28,353.60
$4,678,245.57
FURMAN PARK TOTAL
$4,422,745.00
$5,882.25
$71,035.20
$7,735.10
$16,027.28
$0.00
$29,218.73
$0.00
$38,138.26
$59,110.15
Total Construction Contract cost
$6,955,436.76
Consultant Services — Design
$642,446.00
Construction Management
$ 313,995.00
Inspection, construction supervision, contract administration, abatement $127,785.00
Stora e Containers at Discovery Park
$5,255.00
PROJECTTOTAL • 1 i ,
■ 11 1 s
ACCEPTING COMPLETION OF DISCOVERY PARK AND FURMAN PARK IMPROVEMENTS PROJECT (CIP NO.
19-30 AND CIP NO. 19-31) AS COMPLETE AND AUTHORIZING THE ASSISTANT CITY MANAGER TO ISSUE
AND FILE A NOTICE OF COMPLETION
JULY 28, 2020
PAGE 5
Account No. Fund ..., Cost
Amount
33-1-3350 Measure S $ 5,400,000 $ 5,391,626
TOTAL PROJECT FUNDING $ 8,000,000 $ 8,030,672
1yrri Iit�-
fT
$ 39,046 $ <30,672> (From unappropriated
Measure S funds)
$ 8,374 $ 8,374 (From Furman Park fund to
Discovery Park fund)
$ 30,672.00 $ 30,672