HomeMy WebLinkAbout10. CIP 20-29-Accept Work for Brookshire Ave at Everest St Traffic Safety Enhancements]MUM0
APP-vioVED 13Y
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNOTY MANAGER
FROM: OFFICE OF THE CITY MANAGER
BY: DELFINO R. • P.E., DIRECTOR • PUBLIC WORKS/C14 NGI R
DATE: MAY 26, 2020
SUBJECT: ACCEPT WORK FOR BROOKSHIRE AVENUE AT EVEREST STREEET TRAFFIC
SAFETY ENHANCEMENTS, CAPITAL IMPROVEMENT PROJECT20-
29
That the City Council:
Accept work for Brookshire Avenue at Everest Street Traffic Safety Enhancements,
CIP No. 20-29;
C. Authorize Public Works Director/City Engineer to file Notice of Completion with the
Los Angeles County Recorder's office.
0—
A IBM=
U114) r—Rizi 101 or -IN
E-'iM
CAPITAL IMPROVEMENT PROJECT NO. 20-29
BROOKSHIRE AVENUE AT EVEREST STREET SAFETY ENHANCEMENTS PROJECT
MAY 26, 2020
PAGE #2
Quality of Life, Infrastructure & Parks
The final cost of the construction contract, including base contract amount and change orders, is
$60,207.66. The total final cost of the project is $78,220.66, broken down as follows:
Item Amount
Base Construction Contract Amount $53,445.00
Chafe Orders $6,762.66
.,W.. _......
Final Construction Cost $60,207.66
Design $9,430.00
Construction Inspection $3,967.00
_Construction Engineering_ and Contract Administration $4,616.00
Total Final Project Cost: $78,220.66
Sufficient CIP funds are available to cover the total project cost as shown in the following table:
Account
o. Funding Source
1-6454 Gas Tax Fund (Expended in FY 2018-19)
30-1-6454 Gas Tax Fundj
(��qg,pted.-in.,F,Yl,.12.01.,9.-.20)1--.,.--.---,-....,-,---,.-,-.,.�m
Attachment A — Plans
F171 .7n
I
I
BUTTNTO
MRM CIN
lllmw�
SCALE: r 20'
EVEREST
DEj PgLE
eftok-S,VIRE.
a-N-S-7 Q Cn 0 —NN 0 T E S
El
Tj
v 3
C7111A. Pc.au
I.—
DETAIL V POLE -Q.AND
A VENUE
GENERAL N07E
SMEET
—11. dN6 F-1
M F D C'W Y w.GITY,,QF jr.�
IT
�WNFY
�� Mtill,
EE)-