HomeMy WebLinkAbout05. CIP 19-11 Award Contract w-CJ Concrete Const - Annual Misc Concrete Const & Repair & ADA Imp Proj Dist 4item rto.
APPROVED BY
TO: HONORABLE MAYOR AND MEMBERS OF THE CITYCOUNCIL CITY MANAGER
FROM: OFFICE OF THE CITY MANAGER
D•RO/4
BY: ELFIN. CNSUNJI, P.E., DIRECTOR OPOR
F UBLIC WKS/CITYEi6 NEE
DATE: NOVEMBER 12,2019
SUBJECT: AWARD CONSTRUCTION CONTRACT FOR THE ANNUAL MISCELLANEOUS
CONCRETE CONSTRUCTION AND REPAIRS (COUNCIL DIST-
r .
DISABILITIES ACT (ADA) IMPROVEMENTS (CITYWIDE),
CAPITAL IMPROVEMENT PROJECT NO. 19-11
1 . Award construction contract in the amount of $379,673.50 to CJ Concrete Construction,
Incorporated for the Annual Miscellaneous Concrete Construction and Repairs (Council
District 4) and ADA Improvements (Citywide), Capital Improvement Project No. 19-11;
2. Authorize transfer of $226,050 of budgeted Gas Tax funds from Account No. 30-1-6788 to
Account No. 30-1-6761 to cover shortfall in funding;
3. Approve agreement with the Downey Unified School District (DUSD) for parkway
improvements adjacent to various school campuses;
4. Authorize City Manager to execute the agreement and any amendments to the agreement
deemed necessary in a form acceptable by the City Attorney;
5. Appropriate additional $30,000 in DUSD reimbursable funds in Account No. 26-1-6761 to
cover shortfall in funding; and
6. Authorize Public Works Director to execute any change orders or additional scope of work for
this project deemed necessary or desirable up to the approved project budget.
The City receives requests on an on-going basis for the repair of concrete improvements within the
public right-of-way. These requests are primarily related to damaged and/or uplifted sidewalks; and
curb and gutter; damaged driveway approaches; and uplifted pavement. Priority of repairs is given
areas which have higher than usual pedestrian traffic (i.e. near hospitals, health clinics, schools,
parks, bus stops, and senior care facilities) or locations with severe damage. Periodically, the City
also receives requests for the construction of sidewalks and ADA -compliant curb access ramps
where they currently do not exist.
CAPITAL IMPROVEMENT PROJECT NO. 19-11
ANNUAL MISCELLANEOUS CONCRETE REPAIRS AND ADA IMPROVEMENTS PROJECT
NOVEMBER 12, 2019
PAGE 2
In order to complete the necessary concrete repairs and ADA improvements in a systematic manner,
the City adopted an Annual Concrete Repair Program in which the City was divided into four areas
representing the Council Districts as shown on Attachment A. Each fiscal year, the program is
implemented in a specific Council District and ADA improvements are made Citywide.
Staff has reviewed and evaluated requests received from the residents for concrete repairs and
locations identified in the City of Downey's Self -Evaluation and Transition Plan for ADA related
upgrades. Consequently, locations requiring concrete repairs and/or ADA -related upgrades have
been selected which are in need of immediate attention.
In order to take advantage of economies of scale, the Downey Unified School District (DUSD) has
approached the City requesting parkway improvements adjacent to five DUSD school campuses that
will be funded by DUSD. The parkway improvements will remove continuous landscaped areas
within the parkways located adjacent to the schools which typically consist of turf in poor condition
with dead patches and replaced with new sidewalks for use by students, faculty and visitors walking
to and from the school campuses.
On July 23, 2019, the City Council approved the plans and specifications (Attachment B) and granted
authority to advertise for bids for the Annual Miscellaneous Concrete Construction and Repairs and
ADA Improvements. The project was advertised in the Downey Patriot on August 8 and August 15,
2019, posted on Planet Bids on August 15, 2019, and published in various trade publications.
The work to be completed consists of miscellaneous concrete construction and repairs in Council
District 4 and ADA improvements Citywide including reconstruction of sidewalks, driveway
approaches, curb access ramps, and curb and gutter at approximately 130 locations. In addition, this
project will install parkway improvements adjacent to five DUSD school campuses, namely: Doty
Middle School, Stauffer Middle School, Gauldin Elementary, E.W. Ward Elementary and Lewis
Elementary School.
On August 29, 2019, the City Clerk received and publicly opened nine bids with the base bids ranging
from $190,650 to $298,860 (Attachment C). The bid results were as follows:
CONTRACTOR
CJ Concrete Construction, Inc.
S&H Civil Works, Inc.
EBS General Engineering, Inc.
CT&T Concrete Paving, Inc.
FS Contractors, Inc,
---------- -- -- - - ---- ------ - - --- -
Vido Samarzich, Inc.
Martinez Concrete, Inc.
Kalban, Inc.
Gentry General Engineering, Inc
BASE BID
LOCATION AMOUNT
_..Santa Fe Springs, CA $19.0,65....,6 -
50.00
Colton, CA $195,750.00
Corona, CA $215,054.03
Diamond Bar, CA
Sylmar, CA
Rancho Cucamonga, CA
Azusa, CA
Santa Clarita, CA
Rancho Cucamonga, CA
$222,975.00
$235,650.00
$258,500.00
$262,315.00
- $270,875.00
$298,860.00
BASE BID
AMOUNT PLUS
ADDITIVE BID
ITEMS
$379.673.50
$358,785.00
$442,691.28
$452,855.00
$413,145.00
$476,619.00
$454,833.00
$482,378.00
$501,096.30J
2
CAPITAL IMPROVEMENT PROJECT NO, 19-11
ANNUAL MISCELLANEOUS CONCRETE REPAIRS AND ADA IMPROVEMENTS PROJECT
NOVEMBER 12, 2019
PAGE 3
As specified in the bid documents, the lowest responsible bidder shall be determined on the basis of
the sum of the total base bid items. Consequently, the lowest responsible bidder was CJ Concrete
Construction, Incorporated of Santa Fe Springs, California with a total base bid of $190,650. CJ
Concrete Construction's bid included a total amount of $189,023.50 for the additive bid items for the
DUSD parkway improvements adjacent to five campuses. Thus, CJ Concrete Construction's total bid
amount (total base bid plus additive bid items) was $379,673.50 (Attachment C). Staff reviewed the bid
proposal and references provided by CJ Concrete Construction and found that said contractor has
satisfactorily completed similar projects for the Cities of Cerritos, Downey, La Habra, Long Beach,
Lakewood, Orange and West Covina. CJ Concrete Construction's State of California Contractor's
License is "current and active". In addition, CJ Concrete Construction is registered with the California
Department of Industrial Relations under the Public Works Contractor Registration Program for Labor
Compliance. Staff recommends that the City Council award a construction contract in the amount of
$379,673.50 to CJ Concrete Construction, Incorporated for the construction of the Annual
Miscellaneous Concrete Construction and Repairs and ADA Improvements.
The execution of the agreement with DUSD (Attachment D) will be necessary in order for the City to
construct the parkway improvements adjacent to the five school campuses. In accordance with the
terms of the agreement, DUSD's estimated share of costs for the design, engineering, construction
and contingencies is $230,000. In addition, the City shall complete said improvements between
November 25, 2019 and January 3, 2020. The City shall be reimbursed by DUSD for actual costs
incurred in constructing the parkway improvements following completion of improvements and filing
of Notice of Completion.
Construction is anticipated to begin in November 2019 and be completed in March 2020. This project
is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) under
Section 15301(c), Existing Facilities.
Quality of Life, Infrastructure & Parks
The total estimated project cost, including construction contract, contingencies, design, inspection,
material testing, construction management, contract administration and tree work is as follows:
Item Amount
Construction Contract ($379,674 u!
LContingencies
55, 326
- .
Subtotal Construction Cost 1$435,000
Design 1$23,950
Construction Inspection, Engineering and Contract Administration 1$46,050
Materials Testing
Tree Work
Grand Total
'$5,000
$10,000
±$520,000
3
CAPITAL IMPROVEMENT PROJECT NO. 1Q'11
ANNUAL MISCELLANEOUS CONCRETE REPAIRS AND ADA IMPROVEMENTS PROJECT
NOVEMBER 12,2019
PAGE 4
Account No. Funding SourcAmounte
-5781 Senate Bill 1 (GB1) Local Return funds (expended FY 18/19)
-6761 Transportation Development Act Article III funds (budgeted FY19/20)
-6761 DUS[)Reimbursable funds (budgeted FY19/2O)
-6761 Transfer Gas Tax funds (from Account No. 30'1-6788) _ _ $ 11 226.O5U-
-0761 ApppnprioheAddibpn8|[}U8DRe|mnbura8b|efunds $30c��000
Staff is requesting that the City Council transfer $226,050 from Account No. 30-1-6788 to Account
No. 30-1-6761 and appropriate additional $30,000 in DUSID reimbursable funds in Account No. 26-1-
6761 to cover the shortfall in funding.
Attachment A — Four -Year Annual Miscellaneous Concrete Repair Program Map
Attachment B — Plans
Attachment C — Bid Summary
rd
City of Downey
Four -Year Annual Miscellaneous Concrete Repairs Program Map
COUNCIL DISTRICT 3 I COUNCIL DISTRICT 4]
FY 2022FY 2019/20
I! COUNCIL DISTRICJ ��IFY
0 0.5
1 Miles
I
I
R
I
PART 1: COUNCIL DISTRICT 4 - j
CITY OF DOWNEY
Dlj,.AiIXMY YI >falvAAA
3FF 6s;ixtia a9 ASi hIIBF�Caxs ;e} iN'3�+Fi9fi pi ie
'4.81° U'86 y 4F8EYP A
__ • ,
I�w�a:�i#��T�3E 4i+Ee �T , .t6�$ d� �i§�i �.. _
Tvl -.
A .. q, 3tl vi.5u311% SH Si ax€x3s5t 3b%€4
�m �Mff, �a-m
�AL 8f tiCii i£ial a.
rl iac.iaa9 i£ad*PS - aCSG+Fi®L>jix `la
OF CITY TY�gq
N Y � ID f
Cdr$ RUC- 9LAM - x-
am Descriolion
Part I (Base Bid): District 4
AMEM=A
August 29, 2019
C.11 concrete Construction Inc. S&H Cpjil Works no EBS General Enann e n n q Inc
P rio a Amount Ame
1
Clearing, 6rading Farkway Hesl oration am
Reseedinq
I
LS
$ 9,500-00
$
2150.00 $
1
7,50000
$
7,50000
$ 32,60403
$
32,60403
2
Remove and Resconslrucl 4-IrrhTlick PCC
Sidewalk and Slab
7,700
SF
$ 7.00
$
54,250.001$
1000
$
77,50000
$
1000
$
77,50000
3
Reme Exisling Improvemenis & Conslrucl PCC
500
SF
$ 23.00
$
11,500.001 $
d
2500
$
12,50000
$
1250
$
6,25000
Curb Ramp wilh Deleclable Warnnq Device-
-1ov
4
Remove and Reconstrucl PCG Curb and One-
800
LF
$ 50.00
$
400100 $
40.00
$
3200000
$
4000
$
32,00000
Fool Geller
5
Remove and Reconstrucl FCC Curb and Two-
800
LF
j
U
$ 5300
$
4? 400.00 $
5000
$
40,00000
$
4150
$
33,X0 00
Fool Guitar
6
Remove and Reconslrucl 4-InchThck FCC
1,000
-;J
$ 7.00
$
7,000.00 $
1500
$
15,00000
$
1500
$
15,00000
Residenial Driveway Approach and Slab
7
Remove and Reconslurct 4 -Inch Thck AC
2,0D0
SF
$ IZOO
$
24,000.00 $
500
$
10,00000
$
900
$
18,00000
Paveoul
- 8 Remove and Re�onsiruci Parkway Drain Deck
j.i'1'h
25
SF
$ 120.00
$
1000.00 $
5000
$
1,25000
$
2000
$
50000
Galvanized SIPPI Andp
al'a
. .... .....
Subtotal Base Bid - Items I to 8
$
190,650.00
$
195,75000
$
215,05403
Part 11 (Additive Bid Items): DUSID Parkways
Clearing, Cradling, Parkway Restoration and
9
I
LS
$ 8,500.00
$
%500.00 $
7,500.00
$
7,50000
$ 26,25000
$
26,25900
Reseecling
10 Unclassified Excavalion
10,850
SF
$ 2.25
$
24,412.50 $
200
$
21,70000
$
500
$
62,93000
11 Consrucl 4 -Inch Thck PCC Sidewalk and Slab
10.850
SF
$ 7.00
$
75,950.00 $
500
$
54,25000
$
550
$
59,67500
12 Remove Exisling Improvements & Consirucl PCC
11200
I
SF $
I
2100
$
27.600.00 $
2500
$
3_000
$
1250
$
15,07000
Curb Ramp with Dejeclable Warning Device
13 Remove and Reconsirucl PCC Curb and Two-
250
1.
LF
$ 65.00
$
I6,250.00 $
50 OD
$
12,500 00
$
5800
$
14,50000
Fool Gutter
14 Remove -and Resconsirucl 6 -Inch Thick POC
920
SF
$ 9.50
1
$
8,740.00 $
1509
$
13,80000
$
1500
$
13,9M 00
Commercial Dnvewav Approach and Slab
15 Remove and Reconslrucl'4-tnch Thick FCC
1,200
SF
$ 9.00
$
10,800.00 $
1000
$
IZOOOOO
$
1400
$
16,00000
Sidewalk
16 Adjusl Ulilily Boxes I Covers I o New Finiished
11
EA
$ 500.00
$
5,50000 $
50000
$
5,50000
$
99450
$
10,93950
Grade
17 Remove and ResGonsIrLrI 4 -Inch Thck AC
425
SF
$ 15.00
$
6,375.00 $
500
$
2,12500
$
1075
$
4,56975
Paveoul
18 Remove Exi sli ng PCC Driveway and Consl ruct 4-
126
SF
$ 16.00
$
2,016.00 $
1000
$
1,26000
$
2100
$
2,64600
Inch PCC Sidewalk
19 Sawcul Tree Well and Remove Potion ofExisling
48
SF
$ 60.00
$
2,80100 $
5000
$
2,40000
$
1100
$
52900
FCC Sidewalk
Subtotal Additive Bid Items - Items 9 to 19
$
189,023.50
$
163,03500
$
227,63725
Grand Total Base Bid & Additive Bid Items- touns 1 to 19
$
379,673.50
$
358,78500
i
$
442,69128
ALL BIDS RECEIVED:
CONTRACTOR
TOTAL BASE BID
CJ Concrele ConsiructioR Ind
$
190,65000
S&H Civil Works, Inc.
$
195,75000
EBS General Enginneiing, Inc
$
215,05403
FS Conlraclors, Inc
$
235,65000
CT&T Concrete Paving Inc
$
222,97500
MdoSamarzicl} Inc
$
258,5DO 00
Martinez Concrete, Inc.
$
26Z31500
Kalban, Inc
$
270,87500
Gentry General Engineering Inc
$
29Q 860 00
U9
1411110 :1"011:1
1 :4 VA -1-111m: 10=181
t'EL"L'AL' 1- 1`111 VAIL"
WHEREAS, City is a municipal corporation and charter city and District is a public
school district organized and existing under the laws of the State of California;
WHEREAS, City and District agree that it is in their mutual best interest to provide for
the timely design and construction of parkway improvements along Florence Avenue,
Chaney Avenue, Woodruff Avenue, Spry Street, Dunrobin Avenue, Barlin Avenue, Adoree
Street, Blodgett Avenue, Bellflower Boulevard, Foster Rd, and Old River School Road
("Improvements") which fronts District's school campuses, namely, Doty Middle, Gauldin
Elementary, E.W. Ward Elementary, Lewis Elementary, Stauffer Middle Schools and any
other sites as determined by the District as set forth in Section 3.02;
WHEREAS, City and District agree that the construction by City of the Improvements
in front of District's school properties, shall be subject to reimbursement by District, in the
manner provided herein, is the most efficient and economical method of providing such
public facilities; and
WHEREAS, by entering into this Agreement, the Parties wish to set forth their
understanding related to the standards, timing, construction of the improvements as well as
reimbursement from the District to City for actual costs incurred for constructing the
improvements.
I N
1r-3 H al ffe Ma
1.01: "Improvements" means those improvements set forth in Exhibit
through e. only) attached hereto and incorporated herein by this reference.
11111VIIINIMI 1111 111111pim !J III I
SUEZ==
The Parties agree that it is in their mutual best interest to provide for the timely construction
of the public Improvements to provide access and service to the various school sites and to
serve the residents of the District and City. As a result, the Parties agree that City and its
LhakiII-- dAepm V-&@ A- kq&k11&.VW ...........•.... I I .......•....... r,•- I
WIN 01110MAWAS 1M. M, 1"111, 1111a Wl"t"
its
MMM=
The total Budget for the design, engineering, construction and contingencies of the
Improvements as set forth in Exhibit "A" is estimated at Two Hundred Thirty Thousand
dollars and 00/100 ($230,000.00) ("Budget Estimate of Cost"), which has been approved by
the District. District shall reimburse City for the actual costs incurred by City, including
design, engineering, construction, construction management and inspection and
contingencies.
UMMK��-10 M
In the event that District elects during the course of construction of the Improvements to
include items not called for in Exhibit "A" or not contemplated by the approved Budget
Estimate of Cost, City shall prepare a scope of work and estimate of costs and submit to
District for consideration. If District elects to proceed with the additional site, it shall bear the
'RZI I Lim q 11:2 Fj RI 19 Lela M Lela 101140-41PIMI MR) T 0
M*:T-*-21W-jr-j 17-ITO 0 a GAIN -
"NII WOU-111011
The Budget for the Improvements of this Agreement may be increased by written
amendment to this Agreement signed by the City and the District prior to the start of the
change order work.
1 V
within thirty (30) calendar days of submission of the Accounting of is as set forth in
Paragraph 3.03 above.
A. Notices pursuant to this Agreement shall be given by personal service or 12
deposit of the same in the custody of the United States Postal Service, postage prepaid
addressed as follows:
TO CITY: City of Downey
11111 Brookshire Avenue
Downey, CA 90241
Attn: Gilbert A. Livas, City Manager
TO DISTRICT: Downey Unified School District
11627 Brookshire Avenue
Downey, CA 90241
Attn: Christina Aragon, Associate Superintendent of
Business Services
B. Notices shall be deemed to be given as of the date of personal service, or two
(2) days following the deposit of the same by first class mail in the course of transmission of
the United States Postal Service.
5. Indemnification.
of action and demands, including reasonable attorney fees and costs, incurred in connection
with or in any manner arising out of any claim by any individual or entity against District
forth in this Agreement. City shall, at City's own expense and risk defend any and all
actions, suits, or other legal proceeding that may be brought or instituted against District, its
officers, agents, and employees for any such claims, damages, losses, demands, liabilities,
costs or expenses arising from City's construction of the Improvements as contemplated in
this Agreement. City shall not be obligated to defend, indemnify or hold the City harmless in
2ny manner whatsoever for any claims or liability arising out of the District's own negligent
2.cts, errors or omissions or willful misconduct.
6. Complete Aareernent.
W110101 111101111 W611W W1111--10111WIM11W, F., NFAIN
rall a MmITIVAr-le p!r-gs 1 a ra a a Is At ;I Ole -l -r-1 A I rm Lei I a !ATALI IV
,M Wq I a yKa I I L" IN go I Lei an I I I 819as Ira$ I a mr-1
binding.
7, Atiorney§: Foes.
1ILTARft ROUIL41 =-TA L H PINJIVINAtual
8. Bindinq Awom-merit
1 OWN 'A
W I W -•W -1111110111WIS"
_ZROM. 56111111110 mit
remaining parts, terms and provisions shall not be affected thereby and said illegal,
unenforceable or invalid part, term or provision will be deemed not to be a part of this
Agreement.
10. Modification.
This Agreement may not be altered, amended or modified or changed in any respect or
particular whatsoever except by a writing duly executed by all Parties hereto.
11. Pilo Construction Aciainst Drafter of Agfqprneni.
W1, I W INT R" -we I'll 4 Iowa 1111111 Two "41141"I"W"
this Agreement or any amendment of
12. Lrite!pLetation of Aqreement,
in
lluun U111, al
9.nd that such person is authorized to execute the Agreement on behalf of such Party.
14. 1-tsura-ice.
It is understood and agreed that City and District maintain insurance policies or self-
:nsurance programs to fund their respective liabilities.
15. Work oxi-D.isthct-PnoVerty-|nyuxmn*e.
To the extent City is required to perform work on District property as part of City's
obligations hereunder, City shall coordinate such work with the designated District
representative and City, shall maintain, or require that its contractors and subcontractors
working on District property maintain general liability insurance in the minimum amount of
$1,000,000 with the District named as an additional insured, with thirty (30) days pre-
oancellation notice to the District. The indemnification obligations set forth in paragraph fiva
(5) above apply to all construction related activities including those conducted on District's
District will execute a right of entry agreement giving City and its contractors and
P.ubcontractors permission to enter onto District Property, as necessary, to construct the
Improvements contemplated in this Agreement.
17.Ratification bythe Parties.
This Agreement is not enforceable until and unless it is approved and/or ratified by
the respective governing bodies ofCity and District.
IN WITNESS WHEREOF, the District has caused this Agreement to be properly
executed and City has caused this Agreement to be properly executed, as of the date
hereinabove set forth.
City of Downey Downey Unified School District
By: By:
Gilbert A. Livas, City Manager Christina Aragon, Associa4
Superintendent of Business Services
F.11 a 1 *111
Maria Alicia
■ CMC, City Cler�—' Sej
APPROVED AS TO FORM: APPROVED AS TO FORM:
*t4'�—
Yvoe M. Abich Garcia, City Attorney General Counsel
Z
a. Dotv Middle School — Remove i parkway turf and construct sidewalkthe
widthfull of ' parkways .li • the school frontage on • ` Avenue, Woodruff
Avenue •: Chaney Avenue.• i concrete improvementsit
southwestconstruct curb access ramps on the southeast corner of Florence Avenue at Chaney
Avenue and i of FlorenceWoodruff Avenue. Remove
Schoolexisting unused concrete driveway and construct 4 -inch concrete sidewalk along
school frontage on Woodruff Avenue.
Remove existing i. ., and construct sidewalk
within the full width parkway along the school frontage on Dunrobin Avenue and Spry
Remove and reconstruct existing driveway approaches along it r •'
on Dunrobin Avenue and Spryrespectively,
constructc. E.W. Ward Elementary School — Remove existing concrete improvements and
'• ramp on •rtheast corner of Barlin Avenue and Adoree Street.
Remove existing concrete improvements and construct 6 -inch thick driveway
approach.
widthd. Lewis Elennentary School — Remove existing parkway turf and construct sidewalk
within the full parkway along i il frontage on BellflowerBoulevard,
Foster 1. i and Priscilla Street. Remove ':..• concrete improvementsand
construct• access ramps on •utheast corner of Bellflower Boulevard i
Priscilla Street.
e. Stauffer Middle School — Remove existing parkway turf and construct sidewalk within
the full width of the parkway along the school frontage on Old River School Road.
Remove existing concrete improvementsand construct curb access ramp.