HomeMy WebLinkAbout07. MP Proj 331 - Accept Complete Stewart and Gray Road Valve Repair#
mROM: OFFICE OF THE CITY MANAGER
BY: DELFINO R. CONSUNJI, P.E., DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
DATE: DECEMBER 11, 2018
SUBJECT: MISCELLANEOUS PROJECT NO. 331 — STEWART AND GRAY ROAD VALVE
REPAIR PROJECT FROM BELLFLOWER BOULEVARD TO WOODRUFF
AVENUE — ACCEPTANCE OF PROJECT
That the City Council:
1. Accept Miscellaneous Project No. 331 — Stewart and Gray Road Valve Repair
Project from Bellflower Boulevard to Woodruff Avenue as complete;
2. Approve the final construction contract amount of $212,200; and
3. Authorize the Director of Public Works to file the Notice of Completion with the Los
Angeles County Recorder's office.
Rpla mek
Existing water valves along Stewart and Gray Road from west of Bellflower Boulevard to
Woodruff Avenue were in need of repair to ensure that the City was able to continue to provide
reliable water for domestic and fire purposes. Due to the repair nature of the water work, the
project was informally bid on September 14, 2018. On September 25, 2018, the City Council
awarded a construction contract for this project in the amount of $134,000 to Williams Pipeline
Contractors, Inc. On October 11, 2018, work commenced and is now complete.
e L 9 LC
Boulevard and Stewart and Gray Road; additional potholing requested by the City; and the
completion of associated asphalt and concrete work.
The project has been completed and staff recommends that City Council accept the project as
complete.
MP NO. 331 - STEWART AND GRAY ROAD VALVE REPAIR PROJECT FROM BELLFLOWER
BOULEVARD TO WOODRUFF AVENUE
DECEMBER 11, 2018
PAGE #2
Efficiency & Adaptability
Quality of Life, Infrastructure & Parks
FISCAL IMPACT
The final cost of the construction contract, including the base contract amount and contract
change order, is $212,200. The total project cost is $245,868.06, which includes the cost of
material testing, line stop contractor, and City furnished materials.
The project is funded by Water Fund Capital Improvement Program Account No. 51-1-676,1
(Attachment A).
ATTACHMENTS
smsm=
iq
MP NO. 331 - STEWART AND GRAY ROAD VALVE REPAIR PROJECT FROM BELLFLOWER
BOULEVARD TO WOODRUFF AVENUE
DECEMBER 11, 2018
PAGE #3
Description
Base Contract Amount
Change Orders
H
iq I l� IIH11111111!R71•, .11, 0 il N I ,
Description
Total Construction Contract Cost
City Furnished Materials
City Furnished Line Stop Contractor
Consultant Services - Materials Testing (Estimated)
TOTAL ESTIMATED PROJECT COST:
Account No. Fund
51-1-6768 Stewart and Gray Road Valve Repair Project Water CIP Accounl
K,