HomeMy WebLinkAbout06. CIP 14-18 - Paramount Blvd Median Island Imprv Proj - Auth to BidItem No.
APPROVED BY
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCI ITY MANAGER
FROM: OFFICE OF THE CITY MANAGER
B
YEN IN Y: DELFINO R. CONSUNJI, P.E., DIRECTOR OF PUBLIC WORKS/Cl ft ER
DATE: DECEMBER 11, 2018
VAI 9 [91 ki k -WA 011 1W4 I I MIN
Woll W I.W 011111101110-10 11 . - - . . - a - - a -
The Paramount Boulevard corridor is a major arterial highway and is one of the heaviest
traveled north -south corridors within the City, accommodating both regional as well as local
traffic. Due to the significance and function of this corridor, Paramount Boulevard is in need of
enhancements related to safety, infrastructure improvements and beautification in order to bring
it up to current standards.
Staff conducted an extensive public outreach process in order to engage the residents and
businesses to ensure that they were aware of the proposed median islands and provide an
#,pportunity to give input and comment on the proposed median islands. Public meetings we
held on April 27, 2016 and June 30, 2016 and staff evaluated the public's input and commen
4�nd incorporated their input as part of the project.
The plans and specifications for the subject project are complete and the project is now ready
for solicitation of bids. The project covers approximately 1.5 miles of roadway and the scope -of -
work for the project includes the following elements:
CAPITAL IMPROVEMENT PROJECT NO. 14-18
PARAMOUNT BOULEVARD MEDIAN ISLAND IMPROVEMENTS PROJECT
DECEMBER 11, 2018
PAGE 2
• New raised landscaped median islands where they currently do not exist;
• The reconstruction of an existing raised median island and replacement of existing
landscaping and irrigation;
• Slurry sealing the asphalt pavement between Alameda Street and Firestone Boulevard;
• Restriping of pavement striping and pavement markings along the corridor;
• Miscellaneous repair of uplifted, damaged or substandard curb, gutter, cross gutters,
sidewalk, driveway approaches and curb ramps; and
• Americans with Disabilities Act (ADA) improvements.
Construction work is anticipated to begin in February 2019 and to be completed in June 2019,
6 LHGTZTKW
Efficiency & Adaptability
Quality of Life, Infrastructure & Parks
The total estimated cost of the project is $3,325,000, broken down as follows:
Description t
------- Toy -
Design$161,135 9�
Construction Contract and Contingency $2,760,000
�Consu
ltant Inspection and Project Management $230,000
Consultant
onsultant Materials Testing $25,000
Construction Engineering and Contract Administration $148,865
........ .. . — ------ ---
Total Estimated Project Cost: $3,325,000
Funding in the amount of $1,710,000 is budgeted in the FY 2018/19 Capital Improvement
Program as shown in the table below. Also shown in the table below are previous FY
expenditures, anticipated transfer and additional appropriation of funds. The total project
funding is broken down as follows:
Account
No.
Fundinq Source
Amount
Re- purposed Federal D emo funds (Budgeted FY
26-1-6701
2018/19)
$519,000
Federal Highway Safety Improvement Program
26-1-6701
(HSIP) Cycle 5 grant funds (Budgeted FY 2018/19)
$300,300
1 32-1-6701
Senate Bill 1 (SB1) funds (Budgeted FY 2018/19)
$40,000
State of California Clean Water State Revolving Fund
26-1-6701
(CWSRF) Program Green Project Reserve grant
$850,700
CAPITAL IMPROVEMENT PROJECT NO. 14-18
PARAMOUNT BOULEVARD MEDIAN ISLAND IMPROVEMENTS PROJECT
DECEMBER 11, 2018
PAGE 3
$37,405
$1,125,000
—$3 14,507
$3,325,000
A detailed project cost summary will be provided at the time of the award of the construction
contract.
ATTACHMENTS
Attachment A - Project Location Map
funds (Pending Award from State - FY 2018/19)
26-1-6701
Gas Tax funds (Expended FY 2014/16)
Repurposed Federal Demo funds (Expended FY
26-1-6701
2017/18)
Measure R Local Return funds (Expended FY
56-1-6701
2014/17)
32-1-6701
Senate Bill 1 (SB1.) funds (Expended FY 2017/18)
Transfer of Measure R Funds (from Acct. No. 56-1-
56-1-6701
6628)
xx-1-6701
_Additional Appropriation of funds
Total Proiect Funding:
$37,405
$1,125,000
—$3 14,507
$3,325,000
A detailed project cost summary will be provided at the time of the award of the construction
contract.
ATTACHMENTS
Attachment A - Project Location Map
CAPITAL IMPROVEMENT PROJECT NO. 14-18
FARAM,#VNT &OWLEVAR1 ME111AN ISLAND) IhlrF?-#leEMENTS rR#JECT
DECEMBER 11, 2018
PAGE 4
w -T -M ff-T N T m -f
w --
q,'[JE
ms
mv- -
oto
QUILL DR
WMEY F
HM
' v Ll
1),,
105MAL
if uoir W x
A:: T
I
1p PAW AV
ERIAL
E�; �-�a NO SCALE
CITY OF DOWNEY
DEPARTMENT OF PUBLIC WORKS ENGINEERING DIVISION
LEEDS S'T
PROJECT: CAPITAL IMPROVEMENT PROJECT No. 14-18
PARAMOUNT BOULEVARD MEDIAN ISLAND IMPROVEMENTS PROJECT
LIMITS: (IMPERIAL HIGHWAY TO FIRESTONE BOULEVARD)
ATTACHMENT A