APPROVED BY
TO.' HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL CITY MANAGER
FROM: OFFICE OF THE CITY MANAGER
BY: DELFINO R. CONSUNJI, P.E., DIRECTOR OF PUBLIC WORKS/CITY EGINE
DATE: AUGUST 28, 2018
SUBJECT: CAPITAL IMPROVEMENT PROJECT NO. 18-17 — PARAMOUNT BOULEVARD
WATER SYSTEM IMPROVEMENT PROJECT FROM FIRESTONE BOULEVARD
TO FLORENCE AVENUE — APPROVE PLANS AND SPECIFICATIONS AND
AUTHORIZE SOLICITATION FOR BIDS
That the City Council approve the plans and specifications and author ze solic tation for bids for
Paramount Boulevard Water System Improvement Project from Firestone Boulevard to Florence
Avenue, Capital Improvement Project No. 18-17.
Water system infrastructure along Paramount Boulevard from Firestone Boulevard to Florence
Avenue is in need of improvements to ensure reliable water service for domestic and fire
protection purposes. Said water improvements are proposed to be completed in advance of
Lo Ir
.. ..........
Plans and specifications for the subject project are complete and the project is how ready for
solicitation of construction bids,
The scope of the water improvements includes the installation of new water mains, valves, and
associated fittings and appurtenances; replacement of existing fire hydrants; installation of
additional new fire hydrants where adequate fire water protection is currently lacking; new
copper water service lines; and replacement of old water meters with new remote -read
2dvanced water meters to help improve water meter reading efficiencies.
Staff recommends that the City Council approve the subject project plans and specifications and
authorize solicitation for bids.
CIP NO. 18-17 PARAMOUNT BOULEVARD WATER SYSTEM IMPROVEMENT PROJECT
AUGUST 28, 2018
PAGE #2
Efficiency & Adaptability
Qualitv of Life. lifr,-
M79 -Mr, ITZ-1w,
The estimated total cost of this project, including t e cost of design, construction, project
administration, inspection, and contingencies is $650,000, There are sufficient funds in FY
2018-2019 Water Fund Capital Improvement Program Account Nos. 51-1-8682 and 51-1-8674
to cover the total project cost.