HomeMy WebLinkAbout4. PLN-18-00002 9553 FirestoneCityofDowney STAFF REPORT
PLANNING DIVISION
DATE: JANUARY 17, 2018
TO: PLANNING COMMISSION
SUBMITTED BY: ALDO E. SCHINDLER, DIRECTOR OF COMMUNITY DEVELOPMENT
REVIEWED BY: DAVID BLUMENTHAL, CITY PLANNE
PREPARED BY: DAVID BLUMENTHAL, CITY PLANNER
SUBJECT: PLN -18-00002 (FINAL TRACT MAP) — A REQUEST FOR APPROVAL OF
FINAL TRACT MAP NO 74567 TO SUBDIVIDE A PARCEL INTO 24
LOTS
LOCATION: 9553 FIRESTONE BLVD
ZONING: R-3 (MULTI -FAMILY RESIDENTIAL)
DISCUSSION
On September 21, 2016, the Planning Commission approved Tentative Tract Map No. 74567
and a Site Plan Review to allow the subdivision of the subject site and construction of 24
residential units. The 48,232 square foot site is located on the north side of Firestone Blvd, east
of Pangborn Ave. The zoning of the subject property is R-3 (Multiple -Family Residential) with a
General Plan land use designation of Medium Density Residential (MDR).
The final map consists of a single common ownership lot with 24 airspace units to be built upon
it. Municipal Code Section 9924 requires that the Planning Commission and City Council
approve the final map prior to it being recorded. Both the Public Works Department and
Planning Division have reviewed the final map and have determined that the map complies with
the requirements of the Subdivision Map Act, the City's Municipal Code, and the project
approvals.
Staff is recommending that the Planning Commission adopt a minute action, thereby
recommending the City Council approve Final Tract Map No. 74567.
EXHIBITS
A. Public Works Memorandum, dated January 3, 2018
B. Final Tract Map No. 74567
S OF DO 11,
Mei ora dt m
C�LrFntn`��
To: Aldo E. Schindler, Director of Community Development
From: Edwin Norris, Deputy Director of Public Works tYL
Date: January 3, 2018
Re: FINAL TRACT MAP 74567 — 9553 Firestone BI
Attached herewith are eight (8) prints of the subject map revision, which has been
completed and certified by Willdan Engineering. The Engineering Division has
checked the revised map for conformance with the revised tentative map as
approved by the Planning Commission through Resolution No. 16-2997 on
September 21, 2016.
Engineering Division offsite improvements have been guaranteed via subdivision
cash deposit to the satisfaction of this office.
Should you have any questions, please contact Office Engineering at (562) 904-
7110.