Loading...
HomeMy WebLinkAbout2. PLN-13-00238 Sprint CUP STAFF REPORT PLANNING DIVISION CITY OF DOWNEY, CALIFORNIA DATE: JANUARY 15, 2014 TO: PLANNING COMMISSION FROM: BRIAN SAEKI, DIRECTOR OF COMMUNITY DEVELOPMENT KEVIN NGUYEN, ASSISTANT PLANNER SUBJECT: PLN-13-00238 (CONDITIONAL USE PERMIT) – A REQUEST BY SPRINT CORPORATION TO INSTALL A WIRELESS COMMUNICATION FACILITY WITHIN AN EXISTING 135-FOOT TALL SOUTHERN CALIFORNIA EDISON HIGH TENSION TOWER, ON A PUBLIC PARK (WILDERNESS PARK). LOCATION: 10900 FLORENCE AVENUE (AIN 8020-001-801) ZONING: C-2 (GENERAL COMMERCIAL) REPORT SUMMARY The proposed Land Use Permit Application (PLN-13-00238) is a request from Sprint Corporation seeking for approval of a conditional use permit to allow the installation of six (6) panel antennas and a two-foot diameter microwave dish antenna on an existing 135-foot tall Southern California Edison high tension tower. Based on the analysis contained within this report, staff feels that all required findings to approve the conditional use permit can be made in a positive manner. As such, staff is recommending the Planning Commission adopt the following titled resolution: A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF DOWNEY APPROVING PLN-13-00238 (CONDITIONAL USE PERMIT), A REQUEST BY SPRINT CORPORATION TO INSTALL SIX (6) PANEL ANTENNAS AND A TWO-FOOT DIAMETER MICROWAVE DISH ANTENNA ON AN EXISTING 135- FOOT TALL SOUTHERN CALIFORNIA EDISON HIGH TENSION TOWER. ADDITIONALLY, SPRINT IS PROPOSING A 320 SQUARE FOOT EQUIPMENT SHELTER AT THE BASE OF THE TOWER, ON THE WILDERNESS PARK PROPERTY LOCATED AT 10900 FLORENCE AVENUE, AND ZONED C-2 (GENERAL COMMERCIAL). BACKGROUND The subject site is an approximately 60,000 square foot parcel that is located on the south side of Florence Avenue, between I-605 Freeway and the San Gabriel River. The site is improved with a public park (Wilderness). It contains several Southern California Edison high tension towers at the northerly area of the park. It is zoned C-2 (General Commercial) with a General Plan Land Use Designation of Open Space. Conditional Use Permit (PLN-13-00238) – 10900 Florence Ave January 15, 2014 - Page 2 The surrounding land uses include San Gabriel River Mid Trail to the west and similarly zoned properties with Edison towers to the north. Little Lake Road is on the east side of Wilderness Park. The south side of the site is improved with single family homes. On November 12, 2013, a representative for Sprint Corporation, Justin Robinson, submitted a Land Use Permit Application for PLN-13-00238 (Conditional Use Permit). Staff completed a review of the application on December 11, 2013, and deemed the application complete. On January 2, 2014, notice of the pending public hearing was sent to all property owners within 500’ of the subject site and the notice was published in the Downey Patriot. DISCUSSION/ANALYSIS The applicant is proposing to install six (6) antennas and one (1) microwave dish antenna to the existing 135-foot high Edison tower. The proposed height of the panel antenna is 53 feet above grade and the microwave dish antenna is at 45 feet. In addition, a new 320 square feet (16’ x 20’) equipment shelter will be constructed at the base of the tower. The height of all antennas will not exceed the height of the existing Edison tower structure (see elevation sheets). Section 9426 of the Downey Municipal Code (DMC) regulates the standards for all wireless communications facilities. Subsection 9426.04(b)(10)(ii) states: “Antennas that are collocated onto an existing standalone/tower facility, or on the side of a building, may be permitted at any height, provided the height of the standalone/tower or existing building is not increased and the antennas do not exceed the existing height of the standalone/tower facility or building”. Staff finds that measured at a height of 53 feet above ground, the public will not notice the new antennas easily. Staff believes that stealthing the antennas and the Edison high tension tower is unrealistic because of the scale of the tower. However, staff feels the tower’s aesthetic impact can be mitigated to an extent by painting all wireless antennas, dish antennas, and equipment shelter to a color that matches it. Furthermore, this proposal is consistent with what other wireless companies have done to install antennas at the sites similar to the subject property. ENVIRONMENTAL ANALYSIS Staff has reviewed the proposed antennas for compliance with the California Environmental Quality Act (CEQA). Upon completion of this review, staff determined that this request is categorically exempt from CEQA, pursuant to Guideline Section No. 15301 (Class 1, Existing Facilities). Categorical Exemptions are projects, which have been determined not to have a significant effect on the environment and have been exempted from the requirements of the California Environmental Quality Act. Class 1, includes minor expansion of uses including this request. It is staff’s opinion the installation of the proposed wireless antenna panels to the existing structure will not have a significant effect on the environment; thereby qualifying for the Class 1 exemption. FINDINGS Pursuant to Municipal Code Section 9824.06, there are four (4) findings that must be adopted prior to the Planning Commission approving PLN-13-00238. A discussion of the findings follows: Conditional Use Permit (PLN-13-00238) – 10900 Florence Ave January 15, 2014 - Page 3 A. The requested Conditional Use Permit will not adversely affect the purpose and intent of this chapter or the City’s General Plan or the public convenience or general welfare of persons residing or working in the neighborhood thereof. General Plan Policy No. 2.7.1 states that the City should “Provide adequate utility and communications infrastructure.” Approving this project will help achieve this policy by increasing the capacity of the existing communications network. B. The requested use will not adversely affect the adjoining land uses and the growth and development of the area in which it is proposed to be located. The subject site is improved with a public recreational park and several Southern California Edison high tension towers. It is zoned C-2 (General Commercial) with the San Gabriel River Trail to the west and similarly zoned properties with Edison towers to the north. The south side of the site is improved with single family homes. Installation of the antenna panels and related equipment cabinets will not affect neighboring land uses due to the nature of the use and the manner in which the proposed project is oriented and designed. Moreover, in order to mitigate aesthetic impacts on surrounding properties, all new panel antennas and microwave dish antenna will be painted to match existing Edison high tension tower structure. C. The size and shape of the site proposed for the use is adequate to allow the full development of the proposed use in a manner not detrimental to the particular area. The subject site can be described as being narrow and deep. It is improved with Edison high tension towers and with public park amenities. The proposed antennas will be attached to the existing 135-foot high tower structure. The location of the antennas, and all related equipment, will not interfere with the use of the property. Thus, the site has sufficient shape and size to accommodate the proposed project. D. The traffic generated by the proposed use will not impose an undue burden upon the streets and highways in the area. The proposed project is an unmanned wireless communications facility, which typically only requires a single site visit once a month for maintenance. The adjoining streets (Florence Avenue and Little Lake Road) have sufficient capacity to absorb any additional traffic the requested use may create. CORRESPONDENCE As of the date that this report was printed, staff has not received any correspondence regarding this matter. CONCLUSION Based on the analysis contained within this report, staff recommends that the Planning Commission adopt a resolution to approve PLN-13-00238 (Conditional Use Permit), thereby allowing the installation and operation of a wireless communication facility (Sprint) on an existing 135-foot tall Southern California Edison high tension tower, subject to the conditions of approval. Conditional Use Permit (PLN-13-00238) – 10900 Florence Ave January 15, 2014 - Page 4 Exhibits Location Aerial Photograph Subject Site Conditional Use Permit (PLN-13-00238) – 10900 Florence Ave January 15, 2014 - Page 5 500’ Radius Map Zoning Map RESOLUTION NO. 14-____ A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF DOWNEY APPROVING PLN-13-00238 (CONDITIONAL USE PERMIT), A REQUEST BY SPRINT CORPORATION TO INSTALL SIX (6) PANEL ANTENNAS AND A TWO-FOOT DIAMETER MICROWAVE DISH ANTENNA ON AN EXISTING 135-FOOT TALL SOUTHERN CALIFORNIA EDISON HIGH TENSION TOWER. ADDITIONALLY, SPRINT IS PROPOSING A 320 SQUARE FOOT EQUIPMENT SHELTER AT THE BASE OF THE TOWER, ON THE WILDERNESS PARK PROPERTY LOCATED AT 10900 FLORENCE AVENUE, AND ZONED C-2 (GENERAL COMMERCIAL). THE PLANNING COMMISSION OF THE CITY OF DOWNEY DOES RESOLVE AS FOLLOWS: SECTION 1. The Planning Commission of the City of Downey does hereby find, determine and declare that: A. An application was filed by Justin Robinson (hereinafter "applicant") requesting approval of a PLN-13-00238 (Conditional Use Permit), to install six (6) wireless panel antennas and a two-foot diameter microwave dish antenna at a height of 53 feet to the existing 135-foot high Southern California Edison high tension tower, on the Wilderness Park property at 10900 Florence Avenue, and zoned C- 2 (General Commercial) (hereinafter “subject property”) (Assessor Identification No. 8020-001-801); and, B. On January 2, 2014, notice of the pending public hearing was sent to all property owners within 500’ of the subject site and the notice was published in the Downey Patriot; and, C. The Planning Commission held a duly noticed public hearing on January 15, 2014 and, after fully considering all oral and written testimony and facts and opinions offered at the aforesaid public hearing, adopted Resolution No. 14- ____, subject to conditions of approval (Exhibit A). SECTION 2. The Planning Commission further finds, determines and declares the environmental impact of the proposed development has been reviewed and has been found to be in compliance with the California Environmental Quality Act (CEQA) and is categorically exempt from CEQA, pursuant to Guideline Section No. 15301 (Class 1, Existing Facilities). SECTION 3. Having considered all of the oral and written evidence presented to it at said public hearings, the Planning Commission further finds, determines and declares that: A. The requested conditional use permit will not adversely affect the purpose and intent of this chapter or the City’s General Plan or the public convenience or general welfare of persons residing or working in the neighborhood thereof. General Plan Policy No. 2.7.1 states that the City should “Provide adequate utility and communications infrastructure.” Approving this project will help achieve this policy by increasing the capacity of the existing communications network. B. The requested use will not adversely affect the adjoining land uses and the growth and development of the area in which it is proposed to be located. The subject site is improved with a public recreational park and several Southern Resolution No. 14-____ Downey Planning Commission PLN-13-00238 (CUP) – 10900 Florence Ave January 15, 2014 - Page 2 California Edison high tension towers. It is zoned C-2 (General Commercial) with the San Gabriel River Trail to the west and similarly zoned properties with Edison towers to the north. The south side of the site is improved with single family homes. Installation of the antenna panels and related equipment cabinets will not affect neighboring land uses due to the nature of the use and the manner in which the proposed project is oriented and designed. Moreover, in order to mitigate aesthetic impacts on surrounding properties, all new antennas will be painted to match existing Edison high tension tower structure. C. The size and shape of the subject property proposed for the use is adequate to allow the full development of the proposed use in a manner not detrimental to the particular area. The subject site can be described as being narrow and deep. It is improved with Edison high tension towers and with public park amenities. The proposed antennas will be attached to the existing 135-foot high tower structure. The location of the antennas, and all related equipment, will not interfere with the use of the property. Thus, the site has sufficient shape and size to accommodate the proposed project. D. The traffic generated by the proposed use will not impose an undue burden upon the streets and highways in the area. The proposed project is an unmanned wireless communications facility, which typically only requires a single site visit once a month for maintenance. The adjoining streets (Florence Avenue and Little Lake Road) have sufficient capacity to absorb any additional traffic the requested use may create. SECTION 4. Based upon the findings set forth in Sections 1 through 3 of this Resolution, the Planning Commission of the City of Downey hereby approves PLN-13-00238 (Conditional Use Permit), subject to conditions of approval attached hereto as Exhibit A, which are necessary to preserve the health, safety and general welfare of the community and enable the Planning Commission to make the findings set forth in the previous sections. The conditions are fair and reasonable for the accomplishment of these purposes. SECTION 5. The Secretary shall certify the adoption of this Resolution. PASSED, APPROVED AND ADOPTED this 15th day of January, 2014. Louis Morales, Chairman City Planning Commission I HEREBY CERTIFY that the foregoing is a true copy of a Resolution adopted by the Planning Commission of the City of Downey at a regular meeting thereof, held on the 15th day of January, 2014, by the following vote, to wit: AYES: COMMISSIONERS: NOES: COMMISSIONERS: Mary Cavanagh, Secretary Resolution No. 14-____ Downey Planning Commission PLN-13-00238 (CUP) – 10900 Florence Ave January 15, 2014 - Page 3 City Planning Commission PLN-13-00238 (CONDITIONAL USE PERMIT) EXHIBIT A – CONDITIONS OF APPROVAL PLANNING 1) The approval of PLN-13-00238 (CUP) permits Sprint Corporation to install six (6) panel antennas at a height of 53 feet and a two-foot diameter microwave dish antenna at a height of 45 feet, on an existing 135-foot high Southern California Edison high tension tower. Additionally, the approval includes a 320 square feet equipment shelter at the base of the tower. The project is located on the northerly area of Wilderness Park, at 10900 Florence Avenue, as shown on the approved site plan and elevations. Any deviations or exceptions from said site plan, other than those authorized by this resolution or those that do not impact other conditions, shall not be permitted without the approval by the Downey Planning Commission. 2) All proposed wireless panel antennas, microwave dish antenna, and equipment shelter shall be painted to match the existing California Edison high tension tower. 3) All panel antennas and microwave dish antenna shall not extend above the Edison tower structure. 4) Approval of this PLN-13-00238 (Conditional Use Permit) shall not be construed to mean any waiver of applicable and appropriate zoning regulations, or any Federal, State, County, and City laws and regulations. Unless otherwise expressly specified, all other requirements of the City of Downey Municipal Code shall apply. 5) The City Planner is authorized to make minor modifications to the approved preliminary plans or any of the conditions if such modifications shall achieve substantially the same results as would strict compliance with said plans and conditions. 6) All conditions of PLN-13-00238 (Conditional Use Permit) shall be complied with before this conditional use permit becomes valid. 7) The owner/applicant shall incorporate a copy of this Resolution No. 14-____ (including Exhibit A – Conditions), into the approved set of building plans. 8) The Owner/Applicant agrees, as a condition of approval of this resolution, to indemnify, defend and hold harmless, at Applicant's expense, City and City's agents, officers and employees from and against any claim, action or proceeding commenced within the time period provided in Government Code Section 66499.37 to attack, review, set aside, void or annul the approval of this resolution, to challenge the determination made by City under the California Environmental Quality Act or to challenge the reasonableness, legality or validity of any condition attached hereto. City shall promptly notify Applicant of any such claim, action or proceeding to which City receives notice, and City will cooperate fully with Applicant in the defense thereof. Applicant shall reimburse the City for any court costs and attorney's fees that the City may be required to pay as a result of any such claim, action or proceeding. City may, in its sole discretion, participate in the defense of any such claim, action or proceeding, but such participation shall not relieve Applicant of the obligations of this condition. Resolution No. 14-____ Downey Planning Commission PLN-13-00238 (CUP) – 10900 Florence Ave January 15, 2014 - Page 4 PUBLIC WORKS/ENGINEERING 9) If applicable, the owner/applicant shall obtain all necessary plan approvals and permits and shall be in conformance with the Standard Plans and Specification for Public Works Construction and as modified by the City of Downey’s Standard Plans and Specifications. 10) The owner/applicant shall be required to complete a construction & demolition (C&D) waste management plan per Article V, Chapter 8 of the Downey Municipal Code. 11) The owner/applicant shall provide that all construction graffiti created as part of this project in the public right of way to be removed. FIRE 12) The applicant/owner shall install a Knox® Rapid Entry System for the project. BUILDING 13) The owner/applicant shall provide that all construction shall comply with the 2014 California Building Code and Title 24 of the California Energy Code. 14) Prior to the beginning construction of the equipment enclosure and installation of antenna panels, the owner/applicant shall obtain all required permits and necessary inspections prior to beginning operation of the site. H:\Community Development\Nguyen\CASES\CUP\2013\10900 Florence (Sprint)\13-00238 reso-approve.doc