HomeMy WebLinkAbout06. On-Call Legal Services Award PSA
AGENDA MEMO
DATE:
November 22, 2011
TO:
Mayor and Members of the City Council
FROM:
Office of the City Manager
By: John Oskoui, P.E., Director of Public Works
SUBJECTON-CALL PROFESSIONAL SERVICES FOR RIGHT-OF-WAY
:
ACQUISITION SERVICES – EXECUTE PROFESSIONAL SERVICES
AGREEMENT
RECOMMENDATION
That the City Council authorize the Mayor to execute a Professional Services
Agreement with Kane, Ballmer & Berkman, for on-call professional services for
right-of-way acquisition.
BACKGROUND
The Public Works Department occasionally completes Capital Improvement projects
which require the acquisition of right-of-way. Such projects typically involve street
widenings in order to provide additional street width to provide more travel lanes and
increase capacity to accommodate traffic volume growth and/or additional sidewalk
width to meet Americans with Disabilities Act (ADA) standards.
Currently, the Public Works Department is in the process of completing the following
projects which involve the acquisition of right-of-way from private landowners:
Lakewood Boulevard Improvements, Phases 3B & 3C
Paramount Boulevard at Firestone Boulevard Intersection Improvements
Bellflower Boulevard at Imperial Highway Intersection Improvements
The Lakewood Boulevard Improvements Project, Phases 3B & 3C will involve
continuous widening along this major arterial between Florence Avenue and Telegraph
Road to provide three travel lanes in each direction to accommodate projected traffic
volume growth as well as widening the corners of major intersections in order to
reconstruct the curb returns to provide a 50-foot turning radius to accommodate truck
turning to facilitate the movement of goods. The street widening for this project will
require the partial acquisition of right-of-way from 20 properties. This project is currently
under design and the professional descriptions of the property acquisitions are currently
being prepared. Exhibits A-1 and A-2 show the location of, and proposed property
acquisitions for this project.
The Paramount Boulevard at Firestone Boulevard Improvements Project involves the
widening of this intersection in order to construct double left-turn lanes in each direction
and an exclusive right-turn lane in the eastbound direction in order to accommodate
projected traffic volume growth at the intersection and widening at each of the four
CITY OF DOWNEY, CALIFORNIA
Mayor and Members of the City Council
On Call Professional Services - Execute Professional Services Agreement
November 22, 2011
Page 2
corners of the intersection to reconstruct the curb returns with 50-foot radii to facilitate
truck turning at the intersection. The street widening for this project will require one full
property acquisition and partial right-of-way acquisitions from four properties adjacent to
this intersection. This project is currently under design and the professional
descriptions for the property acquisitions are currently being prepared. Exhibit B shows
the location of this project.
The Bellflower Boulevard at Imperial Highway Intersection Improvements Project
involves the widening of this intersection in order to construct double left-turn lanes in
the northbound and southbound directions and exclusive right-turn lanes in the
eastbound, southbound and northbound directions in order to accommodate projected
traffic volume growth at the intersection and widening at each of the four corners of the
intersection to reconstruct the curb returns with 50-foot radii to facilitate truck turning at
the intersection. The street widening for this project will require the partial acquisition of
right-of-way from six properties adjacent to this intersection. In addition, the property
appraisals have been completed for each of the six properties and staff is ready to
proceed with offers to the property owner for the partial property purchases. The design
for this project is complete. Exhibit C shows the location of, and proposed property
acquisitions for this project.
The Public Works Department previously had a law firm on retainer for on-call right-of-
way acquisition services. However, the purchase order for this firm expired and staff
subsequently circulated a Request for Proposals (RFP) to four law firms to assist the
Public Works Department with right-of-way acquisition professional services for the
three aforementioned as well as other capital improvement projects for which said
services may also be required in the future.
DISCUSSION
Staff circulated the RFP for the subject on-call professional services on October 5, 2011
to the following four law firms:
1. Mayers Nave 3. Rutan & Tucker, LLP
2. Nossaman, LLP 4. Kane, Ballmer & Berkman
Proposals were received from the four firms on October 21, 2011. Based on a review of
the proposals, staff concluded that Kane, Ballmer & Berkman is the preferred firm to
provide the subject on-call professional services, based on the firm’s qualifications of its
key personnel, relevant experience, competitive hourly rates and check of references.
has provided similar on-call professional services for the Cities of Hermosa Beach,
Culver City and Inglewood; the Alameda Corridor – East Construction Authority; and the
Anaheim, West Covina, San Diego, Whittier, Hawthorne and Santa Barbara
Redevelopment Agencies.
Mayor and Members of the City Council
On Call Professional Services - Execute Professional Services Agreement
November 22, 2011
Page 3
The scope of services will generally involve guiding Public Works Department staff
through the right-of-way acquisition process to ensure adherence to all applicable state
and federal laws and specifically will include reviewing professional descriptions and
property appraisals to ensure just compensation to the property owners, preparing or
reviewing purchase offer letters and staff reports, making presentations and addressing
questions at Planning Commission and City Council meetings, mediating between staff
and property owners, preparing Resolutions of Necessity and any supporting
documents, filing and representing the City on eminent domain actions in the Superior
Court, if necessary, and other services as necessary or required.
The execution of the attached Professional Services Agreement will be necessary in
order to authorize Kane, Ballmer & Berkman to proceed with providing the City with the
subject on-call professional services. The term of the agreement will be for two years
with an option for a renewal of one additional year.
FINANCIAL IMPACT
The subject on-call professional services will be charged to the budgets for the various
capital improvement projects requiring said services for right-of-way acquisition.
Attachments:
Exhibits A-1, A-2, B and C
Professional Services Agreement
S:\AgendaMemosCC2011\11-22-11\On-Call Professional Services Award PSA